← Back to projects

MAR/17/114 66-68 English Street Kingston upon Hull East Yorkshire HU3 2DT #10035 · MAR/17/115

Status: won   Value: £700.00

Address: Kingston upon Hull, HU3 2DT, United Kingdom   View on map ↗

Company: Mr C Roach

Brief:

Erection of Cold Storage Building
Notes
47
Tasks
16
Invoices
0
Contracts
0
Inspections
0

Notes + New note

final cert please megan
enquiry 2020-02-14 11:42:07
Comp cert
enquiry 2020-02-07 13:36:03
New Build Letter added to file - 07/02/20
enquiry 2020-02-07 10:27:06
Follow Up: Ring fire brigade 're report resoonse
enquiry 2020-02-06 11:44:44
mike roach english street 01482 324511
enquiry 2020-02-06 11:35:27
Mike Roach - 01482 324511
enquiry 2020-02-04 11:05:43
ranf fire service no one available requested call back asap jab
enquiry 2020-02-03 12:24:35
Spoke to Mike roach at clients

He is chasing the fire brigade response

We are still awaiting this agreed to chase on Monday next week jab
enquiry 2020-01-31 15:47:16
Waiting for fire response 19.12.19
enquiry 2019-12-19 09:43:18
Can I do comp cert?
enquiry 2019-12-19 09:43:18
Follow Up: Fire plan received
enquiry 2019-12-10 09:55:27
Follow Up: send to fie brigade
enquiry 2019-12-10 09:52:57
Electrical certificates and fire plan received 02.12.19
enquiry 2019-12-02 16:45:31
Informed client that a fire plan needs sending over 28.11.19
enquiry 2019-11-28 10:16:45
Site Inspection: HULL - Completion - Please call beforehand - 01482 319365
enquiry 2019-10-23 13:14:14
Site Inspection: HULL - Pre-plaster - 07714099719
enquiry 2019-08-06 11:03:37
James

Find attached the proposed insulation and fire protection of the internal partitions for your approval.

All external walls will be studded with 100mm timbers with 100mm kingspan and 12.5mm plasterboard.

Regards

Steve Hirst
B.Sc., C.Eng., M.I.C.E.
Director
enquiry 2019-07-23 14:42:05
english street layout scanned in
enquiry 2019-07-23 14:41:24
Site Inspection: HULL - Timbers & insulation - 07949470080
enquiry 2019-07-09 11:21:08
floor layout scanned in
enquiry 2019-06-24 16:05:59
scanned in Find attached drawing and calculations for trimming steel.

James

The stairs are designed with 250 of going and a 170mm rise. Can you give approval on the stair layout and the structural design of the trimming steel.
enquiry 2019-02-06 15:37:31
Steve Hirst
enquiry 2019-02-06 09:54:02
Invoice - See notes
enquiry 2018-06-08 12:25:11
Invoiced and sent to address and email below 08.06.18
enquiry 2018-06-08 12:25:10
Eco Engineering Installations ltd
Unit 53
humber enterprise park
brough
hu15 1xw

esteward@eco-eng.co.uk
enquiry 2018-06-07 15:50:44
Invoiced to C M Roach & Co Ltd - 04.05.18
enquiry 2018-05-04 14:25:26
RE INV
enquiry 2018-05-04 14:22:02
Site Inspection: HULL - Cladding Question
enquiry 2018-04-25 14:25:13
do inv
enquiry 2018-03-27 15:52:29
WRONG ADRESS FOR SENDING INV NOT MATRIX
enquiry 2018-02-21 16:38:04
Please can we send confirmation that the concrete can be poured?
enquiry 2017-11-27 11:06:22
Site Inspection: ring beams ring 1 hour before 07768652447
enquiry 2017-10-02 15:33:08
Site Inspection: HULL rerinmforcement to ring beam
enquiry 2017-09-25 12:49:00
can we change it 1200.net plus vat vat inv cm roach and co ltd frozen sea food specialists english street hull 74 76 english st hull hu3 2dt
enquiry 2017-09-20 14:26:52
mike@cmroach.co.uk
enquiry 2017-09-19 15:34:46
Overdue payment invoice sent 22.08.17
enquiry 2017-08-22 11:22:02
Site Inspection: general inspection any progress
enquiry 2017-07-24 09:53:52
Site Inspection: comm
enquiry 2017-07-24 09:53:02
Site Inspection: general inspection any progress
enquiry 2017-07-19 09:29:17
Site Inspection: general inspection any progress
enquiry 2017-07-12 11:49:35
Site Inspection: general inspection any progress
enquiry 2017-06-26 13:11:53
Invoice 01.06.17
enquiry 2017-06-01 14:58:21
Drainage letter - Acceptable
07.04.17
enquiry 2017-04-10 09:35:47
Site Inspection: comm
enquiry 2017-04-05 13:29:55
Acceptance 30.03.17
enquiry 2017-03-30 20:52:01
The project was marked as 'Won'
enquiry 2017-03-29 10:47:45
The project was created
enquiry 2017-03-29 09:39:02

Tasks

final cert please megan
Due 2020-02-14 00:00:00 · ·
Comp cert
Due 2020-02-07 00:00:00 · ·
Ring fire brigade 're report resoonse
Due 2020-02-03 00:00:00 · high · Follow Up
Can I do comp cert?
Due 2019-12-19 00:00:00 · ·
send to fie brigade
Due 2019-12-10 00:00:00 · · Follow Up
Fire plan received
Due 2019-12-05 00:00:00 · medium · Follow Up
HULL - Completion - Please call beforehand - 01482 319365
Due 2019-10-23 00:00:00 · · Site Inspection
HULL - Pre-plaster - 07714099719
Due 2019-08-06 00:00:00 · · Site Inspection
HULL - Timbers & insulation - 07949470080
Due 2019-07-09 00:00:00 · · Site Inspection
Invoice - See notes
Due 2018-06-07 00:00:00 · ·
HULL - Cladding Question
Due 2018-04-25 00:00:00 · · Site Inspection
RE INV
Due 2018-02-21 00:00:00 · ·
do inv
Due 2017-12-07 00:00:00 · ·
Please can we send confirmation that the concrete can be poured?
Due 2017-11-22 00:00:00 · medium ·
ring beams ring 1 hour before 07768652447
Due 2017-10-02 00:00:00 · · Site Inspection
HULL rerinmforcement to ring beam
Due 2017-09-25 00:00:00 · · Site Inspection