OCT/17/88 33 Dovedale Gardens Leeds West Yorkshire LS15 8UP #10806 · OCT/17/88

Status: won   Value: £450.00

Address: Leeds, LS15 8UP, United Kingdom   View on map ↗

Company: Mr Steve Gisborne

Brief:

Erection of Single Storey Extension to Rear Elevation of Dwelling House
Notes
17
Tasks
10
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Completion certificate 26.01.18
enquiry 2018-01-29 09:46:57
Please send comp cert thank you
enquiry 2018-01-26 13:06:50
Site Inspection: LEEDS - Completion - 07711829223
enquiry 2018-01-25 12:07:42
Site Inspection: LEEDS completion 07711829223
enquiry 2018-01-24 18:27:31
Site Inspection: LEEDS pre plaster crossgates side asap please 07711829223
enquiry 2017-11-27 09:15:42
IN Acceptance received 13/11/17
enquiry 2017-11-13 15:43:46
Site Inspection: site visit 07711829223 owner rang said his builder was told today
enquiry 2017-11-03 13:01:02
Follow Up: Speak JW 're drain
enquiry 2017-11-02 11:51:51
Follow Up: Trial Hole
enquiry 2017-11-02 11:42:34
Site Inspection: LEEDS - dpc owner 07711 829223
enquiry 2017-11-01 13:34:26
Chris Pearson builder 07765474264
enquiry 2017-11-01 13:24:46
Paid 27.10.17
enquiry 2017-10-30 12:32:15
Site Inspection: dpc
enquiry 2017-10-30 12:05:09
Client called - Sending cheque today - 07711829223
enquiry 2017-10-27 11:14:40
Site Inspection: LEEDS - (JB)
enquiry 2017-10-27 11:12:43
The project was marked as 'Won'
enquiry 2017-10-25 11:34:31
The project was created
enquiry 2017-10-25 11:34:19

Tasks

LEEDS - Completion - 07711829223
Due 2018-01-25 00:00:00 · · Site Inspection
Please send comp cert thank you
Due 2018-01-25 00:00:00 · ·
LEEDS completion 07711829223
Due 2018-01-22 00:00:00 · · Site Inspection
LEEDS pre plaster crossgates side asap please 07711829223
Due 2017-11-24 00:00:00 · · Site Inspection
site visit 07711829223 owner rang said his builder was told today
Due 2017-11-03 00:00:00 · · Site Inspection
Speak JW 're drain
Due 2017-11-02 00:00:00 · · Follow Up
LEEDS - dpc owner 07711 829223
Due 2017-11-01 00:00:00 · · Site Inspection
Trial Hole
Due 2017-11-01 00:00:00 · · Follow Up
dpc
Due 2017-10-30 00:00:00 · · Site Inspection
LEEDS - (JB)
Due 2017-10-27 00:00:00 · · Site Inspection