← Back to projects

JAN/19/76 The White Bungalow Hazel Old Lane Hensall DN14 0PZ now known as Jinny Lee Cottage Hazel Old Lane Hensall Goole DN14 0PZ #12276 · JAN/19/76

Status: won   Value: £650.00

Address: Hensall, DN14 0PZ now known as Jinny Lee Cottage Hazel Old Lane Hensall Goole DN14 0PZ, United Kingdom   View on map ↗

Company: Mr MC Lawler

Brief:

Erection of Detached Dwelling & Associated Garage
Notes
30
Tasks
13
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Completion Certificate - 30/06/21
enquiry 2021-06-30 13:50:42
Follow Up: Final cert please
enquiry 2021-06-30 13:50:34
Follow Up: comp
enquiry 2021-06-30 11:32:46
Call: DAVID SAYS HE WONT BE GETTING AIR DONE IN TIME NOW
enquiry 2021-06-28 10:05:02
STAIRS ARE IN ELEC OK BEING SENT
enquiry 2021-06-22 14:04:13
spoke to the client he is arrangiong his own EPC and pressure test as used to work for plasmore and they are doing it for him at mates rates apparentlry told him that staircase is to be fitted next week

rang david zafert informed him pof above jab
enquiry 2021-06-14 14:48:07
Call: owner rang 07510584134 might not bre finished will jb speak to david
enquiry 2021-05-04 14:47:57
Returned clients mobile as requested lefty message to call me back asap jab
enquiry 2021-05-04 14:47:06
07510584134 owner
enquiry 2021-04-29 13:10:09
phone call with builder confirmed epc required
enquiry 2021-04-28 15:37:54
Site Inspection: SELBY is this complete
enquiry 2021-04-28 14:44:41
Final Inspection Letter - 21/04/21
enquiry 2021-04-21 09:59:56
Follow Up: final inspection letter please
enquiry 2021-04-21 09:59:47
Retirement Letter Sent
enquiry 2021-03-05 13:15:59
drainage
enquiry 2021-02-22 15:22:59
Site Inspection: SELBY Drainage AM
enquiry 2021-01-28 10:38:10
rang builder imfprmed him pf need to contact office re completion before july this year david well aware of the position says will not be an issue jab
enquiry 2021-01-05 13:51:44
Follow Up: WC
enquiry 2020-09-23 11:36:33
Site Inspection: Pre plaster
enquiry 2020-09-22 14:31:28
ongoing
enquiry 2020-01-15 11:15:13
Site Inspection: WANTED JAMES FOU PLEASE DO WED WED /THURS DAVID FOUNNDATION STEEL CONCRETE POURINF FRIDAY
enquiry 2019-11-27 11:52:10
Site Inspection: HENSALL - Damp - David 07941958441 (Requested James if possible)
enquiry 2019-07-23 14:03:09
Follow Up: raft
enquiry 2019-02-26 10:19:34
Site Inspection: HENSALL steel in mon/tue pooring mid week
enquiry 2019-02-26 09:33:59
Norman zaifert builder 01405 861818
enquiry 2019-02-25 13:49:13
builder norman zaifert rang says has site stripped and will ring me ready for inspection jab
enquiry 2019-02-11 09:19:23
Drainage letter - Acceptable
08.02.19
enquiry 2019-02-08 13:50:30
Cheque received £780.00
enquiry 2019-02-04 13:58:21
The project was marked as 'Won'
enquiry 2019-01-28 10:22:56
The project was created
enquiry 2019-01-28 10:21:30

Tasks

comp
Due 2021-06-30 00:00:00 · · Follow Up
Final cert please
Due 2021-06-30 00:00:00 · high · Follow Up
DAVID SAYS HE WONT BE GETTING AIR DONE IN TIME NOW
Due 2021-06-23 00:00:00 · · Call
owner rang 07510584134 might not bre finished will jb speak to david
Due 2021-05-04 00:00:00 · · Call
SELBY is this complete
Due 2021-04-27 00:00:00 · · Site Inspection
final inspection letter please
Due 2021-04-21 00:00:00 · high · Follow Up
SELBY Drainage AM
Due 2021-01-27 00:00:00 · · Site Inspection
WC
Due 2020-09-23 00:00:00 · · Follow Up
Pre plaster
Due 2020-09-22 00:00:00 · · Site Inspection
WANTED JAMES FOU PLEASE DO WED WED /THURS DAVID FOUNNDATION STEEL CONCRETE POURINF FRIDAY
Due 2019-11-27 00:00:00 · · Site Inspection
HENSALL - Damp - David 07941958441 (Requested James if possible)
Due 2019-07-23 00:00:00 · · Site Inspection
raft
Due 2019-02-26 00:00:00 · · Follow Up
HENSALL steel in mon/tue pooring mid week
Due 2019-02-25 00:00:00 · · Site Inspection