FEB/19/25 22 Roper Avenue Roundhay Leeds LS8 1LG #12326 · FEB/19/25

Status: won   Value: £750.00

Address: Leeds, LS8 1LG, United Kingdom   View on map ↗

Company: Dr H. Gill & Mr R. Bailiff

Brief:

Part Two Storey Part Single Storey Extension & Loft Conversion
Notes
36
Tasks
16
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Completion Certficate - 20/10/20
enquiry 2020-10-20 15:51:00
Final cert please
enquiry 2020-10-20 15:50:51
Site Inspection: LEEDS - Roof and general
enquiry 2020-03-19 10:50:01
Site Inspection: LEEDS general progress
enquiry 2020-02-21 12:27:53
Site Inspection: LEEDS DPC
enquiry 2020-01-17 11:59:46
Site Inspection: LEEDS Concrete addition to foundation builder 07506911306
enquiry 2020-01-09 08:55:54
Photos recd from builder if additional reinforcement to add another layer if concrete to thicken foundation on file agreed ok to cast concrete and we will return at doc level upon request jab
enquiry 2020-01-09 08:54:14
07729 511811
enquiry 2020-01-08 15:25:00
From: info JAB
Sent: 19 December 2019 21:36
To: Stephen Bell
Subject: Roper Avenue


Hi Stephen

Just to keep you up to speed with the above job

I have been on site today and the whole of the extension works other than the steel goal post has been removed

The roof has been striped and currently has felt and battens only

No sure if you have been on site since our last meeting with the client but all our worst fears were realised when the work was removed from site

I have agreed that the existing foundations can be increased in thickness with the provision of dowel bars in to the top resin fixed into the concrete and a layer of A252 Mesh over the whole of the foundation

The foundations to the goal post arrangement have been recast and look much better

One had been cast over the manhole as thought

Beyond belief what the last contractor did

New contractors on site Phoenix seem better and are cooperating with us

I will keep you informed of progress and trust the same from yourselves

Have a good holiday

We finish at 1200 tomorrow back on the 6th January

Kind regards

James


Kind Regards
James
enquiry 2020-01-06 13:27:24
spoke to builder agreed to attend site wed to inspect addition propodsed reimforcment to additional proposed founfations jab
enquiry 2020-01-06 10:10:18
Site Inspection: LS8 LEEDS - Footings exposed - AM if possible please - Please call - Builder: 07729 511811
enquiry 2019-12-19 13:37:11
george robs father 07850982093
enquiry 2019-11-25 13:51:44
Follow Up: report, rob 0113 322 2253
enquiry 2019-11-04 08:49:32
Can this have comp cert?
enquiry 2019-10-29 09:55:32
Call: PLEASE CALL TO ARRANGE MEETING - 07855 550191
enquiry 2019-10-25 14:00:09
Remember to put all photos on later
enquiry 2019-10-25 08:04:48
Site Inspection: JB LEEDS - Roundhay - Wants to meet Structural engineer William Marshall on site, no time confirmed - 07738226823
enquiry 2019-10-23 08:54:59
Site meeting with client and agent and structural engineer

Outlined my concerns yo all 're the state if the works in site

Agent and structural engineer in agreement that works on site in no way demonstrate compliancecwith building regulations in any way

Obviously the works are not fit for purpose and legal action has commenced from the client to the builder

Following additional works noted on site

Mortar sample angle is recd done by client sample fails tovacjievecany classification so serious fail

Wall ties not frewuentvenough in the cavity wall construction

Hard-core to dub floor dips chalk poor quality and has started to turn to mush under foot due to prolonged exposure to elements

The steel coloum have been provided with inadequate foundations one cast on top of the existing msn hole on ditevexposed by clients father structurally inadequate as confirmed by engineer on site

All points noted on previous inspection agreed as valid issues by all concerned

Loft conversion steel frame not oprprn for inspection when seen weld not suitable

Unable to feryfi or otherwise the presence if the required ridge beam

Insulation jbsdequatw to walls and roof of the loft

Hesdroomninadequste to thevstsircase

In general the opinion of all professionals in sitecwas that the works were so poor that demolition and rebuild were the only options available to ensure compliance with regulations

To write to the client copy in all concerned with my response following today's meeting

Weather is dull but dry 12 degrees jab
enquiry 2019-10-22 17:22:08
Site Inspection: LEEDS - Full general inspection because the builder never asked us to come out - Pease call beforehand - Client: 07738 226823
enquiry 2019-10-08 09:02:32
Meeting: Talk to mjf about this one
enquiry 2019-10-07 14:52:25
Site Inspection: LEEDS GENERAL INSPECTION PM 1600HRS 01133222253
enquiry 2019-10-04 09:52:28
client rang office is to change buiders not happy with the work agreed to inspect the work as shown and advise on progress made

imformed him of the lack of inspection due to no requests from the nuilders

jab
enquiry 2019-09-24 11:34:20
0113 3222253
enquiry 2019-09-24 11:03:33
Red kite builders
enquiry 2019-09-20 15:20:08
Site Inspection: LEEDS Roundhay - General Inspection - see notes
enquiry 2019-09-16 17:39:39
Text from client says on holiday at the momemtvabroad but will cont a t me on his return 're issues on site sound responsible vlient
enquiry 2019-08-08 09:35:44
Rang neighbours mobile number given no answer left message to call me back
enquiry 2019-08-05 18:23:47
Called on site following phone call from neighbour regarding progress on site and referring to Party Wall act matters

Works have progressed on site on the side and rear extension without the benefit of inspection by jabai no requests for inspections have been recd from either the builder or the contra tor

Walking to side extension at eaves level rear extension difficult to access burnt steelwork to support the first floor can be seen in position

Clients not in and looks like property may be empty

Site is very messy with materials in the front garden insulation pulled on the drive old rockwool and materials on the grass verge outside the house

To write to the client requesting contact made for progress inspection of the works

Weather is good dry and sunny 22 degrees jab
enquiry 2019-08-05 18:20:49
Alistair Lawson - 07896974837
Next door neighbour - number 20.
Can JB speak to him re the build at number 22.
enquiry 2019-08-05 14:09:32
Drainage letter - Acceptable
07.03.19
enquiry 2019-03-07 14:28:52
Paid cheque 05.03.19
enquiry 2019-03-07 13:49:58
Acceptance 21.02.19
enquiry 2019-02-21 12:21:13
The project was marked as 'Won'
enquiry 2019-02-20 14:27:22
Site Inspection: LEEDS - Footings - Please call half an hour before - 07803359688
enquiry 2019-02-14 18:39:06
Rang and left message on builders phone 're above
enquiry 2019-02-14 18:38:26
The project was created
enquiry 2019-02-13 09:26:31

Tasks

Final cert please
Due 2020-10-12 00:00:00 · ·
LEEDS - Roof and general
Due 2020-03-19 00:00:00 · · Site Inspection
LEEDS general progress
Due 2020-02-21 00:00:00 · · Site Inspection
LEEDS DPC
Due 2020-01-17 00:00:00 · · Site Inspection
LEEDS Concrete addition to foundation builder 07506911306
Due 2020-01-09 00:00:00 · · Site Inspection
LS8 LEEDS - Footings exposed - AM if possible please - Please call - Builder: 07729 511811
Due 2019-12-19 00:00:00 · · Site Inspection
report, rob 0113 322 2253
Due 2019-10-29 00:00:00 · · Follow Up
Can this have comp cert?
Due 2019-10-25 00:00:00 · ·
Remember to put all photos on later
Due 2019-10-24 00:00:00 · ·
JB LEEDS - Roundhay - Wants to meet Structural engineer William Marshall on site, no time confirmed - 07738226823
Due 2019-10-22 00:00:00 · · Site Inspection
PLEASE CALL TO ARRANGE MEETING - 07855 550191
Due 2019-10-21 00:00:00 · · Call
LEEDS - Full general inspection because the builder never asked us to come out - Pease call beforehand - Client: 07738 226823
Due 2019-10-08 00:00:00 · · Site Inspection
Talk to mjf about this one
Due 2019-10-07 00:00:00 · high · Meeting
LEEDS GENERAL INSPECTION PM 1600HRS 01133222253
Due 2019-10-01 00:00:00 · · Site Inspection
LEEDS Roundhay - General Inspection - see notes
Due 2019-08-05 00:00:00 · · Site Inspection
LEEDS - Footings - Please call half an hour before - 07803359688
Due 2019-02-14 00:00:00 · · Site Inspection