SEP/19/84 (Rear Extension) 13 The Rowans Baildon Shipley BD17 5DB #13110 · SEP/19/84

Status: won   Value: £100.00

Address: Shipley, BD17 5DB, United Kingdom   View on map ↗

Company: Mr Nicholas John Barber

Brief:

Single Storey Extension to Rear of Dwelling House
Notes
16
Tasks
7
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Final cert please
enquiry 2020-08-07 11:58:18
Site Inspection: SHIPLEY BD17 5DB completion
enquiry 2020-08-06 12:54:05
Site Inspection: BAILDON - Insulation - 07456 445101
enquiry 2020-01-27 13:25:03
Follow Up:
enquiry 2020-01-20 12:45:34
pd bac 06/12/19
enquiry 2019-12-11 11:16:39
Call:
enquiry 2019-12-03 08:50:29
From: Nick Barber
Sent: 26 November 2019 17:55
To: Glynn O'Malley
Subject: 13 The Rowans, gap for Kingspan & suitable damp proof protection - site visit booked for 28/11/19

Hi Glynn,

Further to our call this afternoon, I’ve taken your advice and have called the office to make an appointment for you to visit my site to inspect on Thursday 28th November.

The aspects which are concerning to me and which I’d like your instruction on are:

1/ drainage - a bridge has been built (you know about this already and have given oversight) to allow the existing land drains to snake through the underneath of the side extension walls. Is this sufficient to allow water run off from the rear garden (and sloping field behind) to dissipate? I’m concerned that a blockage could result in a build up of water under the side extension floor.

2/ damp proofing of side elevation of side extension - the exterior soil level is higher than the interior floor level by around a 500mm. Please can you check and advise whether appropriate damp proofing has been applied to the side elevation walls or whether any further protection is required? Potentially the builder will run a land drain pipe, buried under soil, to run adjacent to the side elevation wall. Please can you also check and advise whether this is an acceptable plan and if so whether this land drain pipe needs any additional protection and whether it requires burying in a gravel mixture rather than just soil butting up to the wall?

3/ rear elevation wall of side extension - the exterior corner wall is part built but doesn’t appear to leave enough gap for 150mm kingspan insulation to be inserted between the exterior stone and interior block work. In fact some exterior stone is so close that it touches the interior block work - this is a worry re damp penetration. Please see photo attached and advise how this can be made right?



4/ rear elevation wall of side extension - the part built new pillar adjoining the existing property wall doesn’t look square, and I don’t think will line up square to the block work which continues after the patio door gap. Can you check and advise?

Thanks,
Nick
07456445101
enquiry 2019-12-02 11:26:27
Site Inspection: BAILDON - Block work - Spoke to Glynn - Please call beforehand - Client: 07456 445101
enquiry 2019-11-28 16:54:12
From: Glynn O'Malley
Sent: 27 November 2019 09:01
To: Nick Barber
Subject: Re: 13 The Rowans, study to garage 900mm knock through

Nick

No problem.

I have no issues with the knock through or the work completed from the visual inspection completed via your photos. FD30 fitted which is good. The steel being replaced with the Catnic lintel looks fine albeit 'as always' when making a design specification change from an engineers drawing / or their calculations the builder should always get approval from the design engineer as a must. That is just normal construction and engineering management protocol as the design engineer is taking on design liability. Otherwise there isn't any point have the calcs or drawings done in the first place.

One observation around the fd30. The builder should have used fire rated (which is pink) intumenscent foam rather than the normal expanding foam variety to seal serviceable gaps. Not sure what you are going to do with the floor access / egress to make it safe so some thought is needed a bit on that one . Let me know of your proposals but it isn't a big issue at this point of time.

Hope that helps.

Give me a call if you need any help.


Regards

Glynn O'Malley BSc(Hons) MSc CBuildE FCABE CMgr CMIOSH MIET CIWFM
________________________________________
From: Nick Barber
Sent: 26 November 2019 17:03
To: Glynn O'Malley
Subject: Re: 13 The Rowans, study to garage 900mm knock through

Hi Glynn,

Further to our conversation; the lintel is a Catnic. Please could you confirm that this is an approved alternative to the steel proposed in the structural engineers drawings / calculations I provided, and that that the brick padstones used is an approved alternatives to a concrete block padstone?

Many thanks,
Nick

Sent from my iPhone

> On 26 Nov 2019, at 10:50, Nick Barber wrote:
>
> Hi Glynn,
>
> Thanks for your time on the phone this morning, as requested please see photos of the knock through from the house to the garage (to give us easy access to a utility area within the garage).
>
> All materials are fire regulations approved. The smoke strips aren’t fitted yet - I’m not sure whether this is because they’ll be fitted after painting. Can you advise on this point?
>
> We’d like to make good as soon as possible. Please let me know if you need any more info / photos, and give me a green light that this meets your standards / building regs and you’re happy for us to make good?
>
> Thanks,
> Nick
enquiry 2019-11-27 09:29:52
Call: builder said you said he could build off the bace owner asked to confirm 07456445101
enquiry 2019-11-19 09:20:15
Site Inspection:
enquiry 2019-11-01 09:23:35
Site Inspection:
enquiry 2019-11-01 09:23:34
Acceptance 30.09.19
enquiry 2019-10-02 16:04:10
Drainage letter - Acceptable
26.09.19
enquiry 2019-09-30 09:31:35
The project was marked as 'Won'
enquiry 2019-09-27 09:32:25
The project was created
enquiry 2019-09-27 09:32:23

Tasks

Final cert please
Due 2020-08-06 00:00:00 · ·
SHIPLEY BD17 5DB completion
Due 2020-08-06 00:00:00 · · Site Inspection
BAILDON - Insulation - 07456 445101
Due 2020-01-27 00:00:00 · · Site Inspection
Due 2020-01-20 00:00:00 · · Follow Up
Due 2019-12-03 00:00:00 · · Call
BAILDON - Block work - Spoke to Glynn - Please call beforehand - Client: 07456 445101
Due 2019-11-28 00:00:00 · · Site Inspection
builder said you said he could build off the bace owner asked to confirm 07456445101
Due 2019-11-18 00:00:00 · · Call