JAN/21/36 9 Roper Grove Leeds West Yorkshire LS8 1LF #13867 · JAN/21/36

Status: won   Value: £500.00

Address: Leeds, LS8 1LF, United Kingdom   View on map ↗

Company: Mr Peter Hollywood

Brief:

Room in Roof Space with Rear Dormer
Notes
25
Tasks
14
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Posted to client - 30/06/21
enquiry 2021-06-30 13:34:06
Site Inspection: Final inspection
enquiry 2021-06-30 13:33:52
Completed sent to council - NOT POSTED TO CLIENT
enquiry 2021-06-30 13:33:08
Site Inspection: final inspection
enquiry 2021-06-23 13:41:26
Completed - sent to council - 21/06/21
enquiry 2021-06-21 11:56:53
final cert please keep client copy send LA
enquiry 2021-06-21 11:56:43
Site Inspection: LEEDS - any progress AKB
enquiry 2021-06-21 09:59:10
Site Inspection: Leeds general
enquiry 2021-06-21 09:59:08
Site Inspection: Leeds general
enquiry 2021-05-19 14:17:41
Final Inspection Letter sent - 13/05/21
enquiry 2021-05-13 11:26:13
Follow Up: Final inspection letter please
enquiry 2021-05-13 11:26:03
Site Inspection: Plastered out
enquiry 2021-05-13 11:25:02
Site Inspection: LEEDS timber frame and stairs
enquiry 2021-05-04 13:36:04
paid
enquiry 2021-04-27 11:20:20
re invoiced
enquiry 2021-04-22 13:06:58
Site Inspection: LEEDS Steelwork in position
enquiry 2021-04-19 13:09:41
AKB ONE
enquiry 2021-04-19 13:07:23
Not started yet, due to start Mid March.
enquiry 2021-04-13 11:53:23
needs scanning in
enquiry 2021-04-08 14:12:46
Retirement Letter Sent
enquiry 2021-03-05 12:21:49
IN Acceptance - 16/02/21
enquiry 2021-02-16 14:28:54
Site Inspection: LEEDS HAS THIS STARTED AKB
enquiry 2021-02-15 14:36:45
Not started yet, starting mid March
enquiry 2021-02-15 14:35:33
The project was marked as 'Won'
enquiry 2021-01-13 12:41:32
The project was created
enquiry 2021-01-13 12:41:30

Tasks

Final inspection
Due 2021-06-30 00:00:00 · · Site Inspection
final inspection
Due 2021-06-23 00:00:00 · · Site Inspection
Leeds general
Due 2021-06-22 00:00:00 · · Site Inspection
final cert please keep client copy send LA
Due 2021-06-21 00:00:00 · ·
Completed sent to council - NOT POSTED TO CLIENT
Due 2021-06-21 00:00:00 · medium ·
LEEDS - any progress AKB
Due 2021-05-25 00:00:00 · · Site Inspection
Leeds general
Due 2021-05-19 00:00:00 · · Site Inspection
Plastered out
Due 2021-05-13 00:00:00 · · Site Inspection
Final inspection letter please
Due 2021-05-13 00:00:00 · high · Follow Up
LEEDS timber frame and stairs
Due 2021-05-04 00:00:00 · · Site Inspection
LEEDS Steelwork in position
Due 2021-04-19 00:00:00 · · Site Inspection
Not started yet, due to start Mid March.
Due 2021-02-24 00:00:00 · ·
LEEDS HAS THIS STARTED AKB
Due 2021-02-15 00:00:00 · · Site Inspection
needs scanning in
Due 2021-02-10 00:00:00 · ·