SEP/15/06 20A BARFF LANE BRAYTON NR SELBY YO8 9ET #8137 · SEP/15/06
Notes
15
Tasks
8
Invoices
0
Contracts
0
Inspections
0
Notes + New note
enquiry 2018-09-12 09:01:26
check notes jb
enquiry 2018-08-08 20:03:08
enquiry 2018-08-08 15:26:32
Completion certificate 07.08.18
enquiry 2018-08-08 14:52:08
enquiry 2018-08-08 11:11:25
enquiry 2018-08-07 15:22:49
enquiry 2018-08-07 15:17:46
Email received back from the client:
Hi Megan, thanks for the email, there seems to have been a communication problem between our builder and your office. The electrician said he could not issue a certificate until our consumer unit was changed for the newer type. As we intend completely renewing the kitchen, which will necessitate some rewiring, it was agreed we would do the rewiring and consumer unit upgrade at the same time. This will happen in the first half of next year, we could not afford the extension and the kitchen in one go. So I don't expect to have the electrical certificate until possibly May 2018. I hope that has cleared the confusion. I can let you know as soon as I get it, if that's ok? Many thanks, Steve.
Hi Megan, thanks for the email, there seems to have been a communication problem between our builder and your office. The electrician said he could not issue a certificate until our consumer unit was changed for the newer type. As we intend completely renewing the kitchen, which will necessitate some rewiring, it was agreed we would do the rewiring and consumer unit upgrade at the same time. This will happen in the first half of next year, we could not afford the extension and the kitchen in one go. So I don't expect to have the electrical certificate until possibly May 2018. I hope that has cleared the confusion. I can let you know as soon as I get it, if that's ok? Many thanks, Steve.
enquiry 2017-10-04 15:00:11
Sent email to client asking about the final inspection - sj917b@gmail.com
enquiry 2017-10-04 11:54:38
enquiry 2017-10-04 11:48:50
enquiry 2017-10-04 11:22:04
Email from client - 15/08/17
Hi, you called to do final inspection, 20A Barff Lane, Brayton, Selby, YO89ET. I thought it had already been done ages ago but anyway its not possible this month because of holidays. Can I contact you in September please to arrange a date? Could you reply by email because I am struggling with depression and using the phone has become a real problem, many thanks, Steve Joyce.
Hi, you called to do final inspection, 20A Barff Lane, Brayton, Selby, YO89ET. I thought it had already been done ages ago but anyway its not possible this month because of holidays. Can I contact you in September please to arrange a date? Could you reply by email because I am struggling with depression and using the phone has become a real problem, many thanks, Steve Joyce.
enquiry 2017-08-15 09:34:44
enquiry 2017-08-03 11:52:29
The project was marked as 'Won'
enquiry 2017-03-15 18:01:40
FEE 350 + VAT
INV 09/09/15
15/09/15 PAID
brayton
01757 706377
enquiry 2017-01-17 16:33:58
Tasks
SELBY completion confusion on thhis one was exspecting us yesterday
BRAYTON - Completion - 01757 706377
compl
Comp cert
Final certificate please megan
Final inspection letter
Get email address from info
site visit