← Back to projects

NOV/15/48 FAIRVIEW CRABTREE GREEN COLLINGHAM LEEDS LS22 5AB #8363 · NOV/15/48

Status: won   Value: £0.00

Address: United Kingdom   View on map ↗

Company: MR S MUNRO

Brief:

TWO STOREY EXTENSION TO REAR AND INTERNAL STRUCTURALALTERATIONS TO DWELLING HOUSE
Notes
16
Tasks
8
Invoices
0
Contracts
0
Inspections
0

Notes + New note

Completion certificate 09.07.18
enquiry 2018-07-09 11:38:16
please send comp cert thank you
enquiry 2018-07-09 09:50:11
Follow Up: Can I do comp cert?
enquiry 2018-07-09 09:33:53
Follow Up: Photos are on Documents - Captioned Photo 1 and Photo 2
enquiry 2018-07-09 09:33:52
please send comp cert thank you
enquiry 2018-07-02 09:40:49
Follow Up: Balustrade
enquiry 2017-11-23 17:21:42
Site Inspection: LEEDS - Completion - 07868709232
enquiry 2017-11-23 12:24:19
07815 323662 Claire owner
enquiry 2017-11-23 12:19:47
Final inspection letter
enquiry 2017-10-26 11:46:34
Final inspection letter sent 26.10.17
enquiry 2017-10-26 11:46:33
site visit
enquiry 2017-10-24 08:49:57
Site Inspection: general inspection whats the progress on this job if any
enquiry 2017-06-06 14:40:03
Site Inspection: general inspection whats the progress on this job if any
enquiry 2017-05-31 13:35:49
Site Inspection: general inspection whats the progress on this job if any
enquiry 2017-04-04 11:44:32
The project was marked as 'Won'
enquiry 2017-03-20 14:27:05
500 IN 19/01/16 paid 23/02/16
enquiry 2017-01-17 16:34:06

Tasks

please send comp cert thank you
Due 2018-07-09 00:00:00 · ·
Can I do comp cert?
Due 2018-07-06 00:00:00 · · Follow Up
Photos are on Documents - Captioned Photo 1 and Photo 2
Due 2018-07-06 00:00:00 · · Follow Up
please send comp cert thank you
Due 2018-07-02 00:00:00 · ·
LEEDS - Completion - 07868709232
Due 2017-11-23 00:00:00 · · Site Inspection
Balustrade
Due 2017-11-23 00:00:00 · · Follow Up
Final inspection letter
Due 2017-10-24 00:00:00 · ·
site visit
Due 2017-08-17 00:00:00 · ·